Haiti - Les Cayes Airport : Modernization work nearing completion - HaitiLibre.com : Haiti news 7/7
 2026-2027 Electoral Calendar, latest official version





P4000+ Program : 2,069 new police officers integrated into the PNH

NOTICE : Recruitment and training of Electoral Security Agents

iciHaiti - Cultures in Solidarity : Mayor of Léogâne visits Saint-Denis, France

Jacmel : Partnership Agreement for the preservation and promotion of historical heritage

Caribbean Cup : Dominicans force the postponement of the Haiti vs. Jamaica semi-final


more news


Haiti - News : Zapping...

Haiti - Politic : Secretary of State Lucien Jura speaks on the current situation (video)

Haiti - Politic : BINUH and GSF report the situation in Haiti to the Security Council

Haiti - FLASH : Guatemala sends additional troops to Haiti

Haiti - FLASH : The 4 Salvadoran soldiers from the burned-out armored vehicle are missing


more news


Haiti - Les Cayes Airport : Modernization work nearing completion


Haiti - Les Cayes Airport : Modernization work nearing completion

The renovation work at Antoine Simon International Airport, launched in September, was 80% complete by mid-December, with an initial delivery date of December 31, 2025.

Compliance with international standards (TSA and ICAO) : These interventions, while temporary pending the launch of the future master plan, aim for immediate and secure operation. A crucial milestone has already been reached: in early December, the airport received approval from the Transportation Security Administration (TSA), officially opening the way for direct flights between the United States and Les Cayes. https://www.icihaiti.com/en/news-46347-icihaiti-les-cayes-good-news-for-antoine-simon-international-airport.html

A task force from the National Airport Authority (AAN) is currently deployed on-site to ensure strict compliance with standards. It is composed of :

  • The International Civil Aviation Organization (ICAO);

  • The Federal Aviation Administration (FAA);

  • The National Civil Aviation Office (OFNAC).

Main terminal improvements :

The project, carried out by the Haitian firm SD Construction S.A. under the supervision of BETA Consulting Engineers, transforms the passenger experience:

  • Improved flow :

    Repositioning of check-in counters and the Security Checkpoint (SCR);

  • Sovereign Services:

    Creation of dedicated areas for immigration (departure/arrival) and customs;

  • Comfort :

    Construction of an international departure lounge, a VIP lounge, and full terminal air conditioning;

  • Logistics :

    New baggage handling area and relocation of Sunrise Airways' ticketing/cargo services.

Security and Technical Infrastructure :

In addition to the terminal, perimeter security work is underway :

  • Installation of a temporary lighting system;

  • Construction of a Road Access and Screening Post (PARIF);

  • Imminent commissioning of technical rooms for IT and video surveillance.

HL/HaitiLibre